Analisis Faktor Keterlambatan Proyek Konstruksi Gedung di Kabupaten Purworejo

Analysis of Delay Factors for Building Construction Project in Purworejo Regencey

Authors

  • Larashati B'tari Setyaning Universitas Muhammadiyah Purworejo
  • Agung Nusantoro Universitas Muhammadiyah Purworejo
  • Sukma Adi Pratama Universitas Muhammadiyah Purworejo

DOI:

https://doi.org/10.32528/hexagon.v9i1.1714

Keywords:

delay, building construction project, exploratory factor analysis (EFA)

Abstract

Basically, construction projects cannot be free from existing obstacles that can cause delays in ongoing projects. Work that experiences problems can cause delays and result in losses and various methods are taken to avoid problems that result in delays and losses. The aim of this research is to analyze the factors that cause delays in construction work on building construction projects in Purworejo Regency and analyze the correlation or relationship between these factors. In this research, data processing uses Exploratory Factor Analysis (EFA) analysis for correlation or relationship between factors causing delays in building construction projects in Purworejo Regency. A set of questionnaires was used to obtain the required primary data. Exploratory factor analysis techniques are used to identify existing latent variables. Questionnaires were obtained from 40 people consisting of contractors, supervisory consultants and owners involved in this research. The results of the research explain that five factors influence delays in building construction projects in Purworejo Regency, namely auction process factors and non-technical events, inappropriate technical planning, accuracy factors in the amount of material sent, communication and coordination factors, equipment productivity factors.

References

Agritama, R. P., Huda, M., & Rini, T. S. (2018). Faktor-Faktor yang Mempengaruhi Keterlambatan Proyek Konstruksi di Surabaya. Axial (Jurnal Rekayasa Dan Manajemen Konstruksi), 6(1), 25–32.

Analysa, D., Suhudi, S., & Rahma, P. D. (2019). Evaluasi Keterlambatan Proyek Pembangunan Graha Mojokerto Service City (GMSC) dengan Metode Fault Tree Analysis (FTA). Reka Buana : Jurnal Ilmiah Teknik Sipil Dan Teknik Kimia, 4(2), 112–119. https://doi.org/10.33366/rekabuana.v4i2.1407

Ariefasa, R., Juanto, S., & Berawi, M. A. (2012). Faktor penyebab keterlambatan pekerjaan konstruksi bangunan gedung bertingkat yang berpengaruh terhadap perubahan anggaran biaya pada pekerjaan struktur.

Boy, W., Erlindo, R., & Fitrah, R. A. (2021). Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Gedung Kuliah pada Masa Pandemi COVID 19. JURNAL RIVET, 1(01), 57–64. https://doi.org/10.47233/rivet.v1i01.231

Ghozali, I. (2018). Aplikasi Analisis Multivariate dengan Program IBM SPSS 25. Badan Penerbit Universitas Diponegoro.

Hassan, H., Mangare, J. B., & Pratasis, P. A. K. (2016). Faktor-Faktor Penyebab Keterlambatan pada Proyek Konstruksi dan Alternatif Penyelesaiannya (Studi Kasus: di Manado Town Square III). Jurnal Sipil Statik, 4(11), 657–664.

Kamaruzzaman, F. (2012). Studi Keterlambatan Penyelesaian Proyek Konstruksi. Jurnal Teknik Sipil Untan, 12(2), 175–190.

Messah, Y. A., Widodo, T., & Adoe, M. L. (2013). Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Gedung Di Kota Kupang. Jurnal Teknik Sipil, 2(2), 157–168.

Puspitasari, Y. I., Mangare, J. B., & Pratasis, P. A. K. (2020). Analisis FaktorFaktor Keterlambatan Pada Proyek Perumahan Casa De Viola Dan Alternatif Penyelesaiannya. Jurnal Sipil Statik, 8(2), 141–146.

Downloads

Published

30-07-2024

Issue

Section

Articles